Skokie Swift Downtown Station is set to open early 2012
By Rich Groh
November 14, 2011
The new Oakton Station is progressing nicely. Roofing installation has begun at the North and South Station Houses. Masonry activities are complete.
The Permanent site road has been installed and the electrical and communication huts have been set in place. Roofing activities will continue over the next few weeks. The bike rack area is taking shape at the pedestrian grade crossing along with many site work activities such as the sidewalks, decorative bricking and site lightingSkokie Swift, Oakton Station
.